A brief summary on the network laid out thus far within the City Of Johannesburg is as follows:
STATUS
Civil Work Status
| |
5 Rings complete |
| |
300km civil work complete |
| |
Obstacles |
| |
N3 & River Crossing & |
| |
Road crossing in Sandton |
| |
Access into buildings |
| |
Damages by other operators/Service providers |
|
Fibre Status
| |
Pre Testing |
| |
Post Testing |
| |
Fibre Blowing – 210km |
| |
Splicing |
| |
End to End Testing |
| |
Damage to ducts – delay in fibre blowing |
|
Fibre Monitoring
| |
Monitored from anderson street |
| |
Remote monitoring |
| |
Demo |
|
| Active Equipment installation – August 2011 |