City of Johannesburg Broadband Network Project being built and operated by BWired Broadband is approximately 30% completed with about 300km of ducting and fibre already in the ground. We estimate that we will have about 940km of fibre laid out once the project is completed. We are currently 3 months ahead of schedule and look to be finished by March 2013.

 

The green line in the route below shows the Core fibre route that has been completed.

Masakhe Joburg Ericsson BCS
© BWIRED, South Africa, 2011